    IRANIAN GAS DELIVERY VIA IRAN-ARMENIA PIPELINE TO START DECEMBER 20

    PanARMENIAN.Net
    25.10.2006 18:38 GMT+04:00

    /PanARMENIAN.Net/ Iranian gas will be received in Armenia via the
    Iran-Armenia gas pipeline earlier than planned, stated Director
    of High-Voltage Electric Grids - the customer, which has ordered
    the building of the Armenian part of the gas pipeline - Sahak
    Abrahamyan. In his words, the gas pipeline is expected to be
    commissioned December 20 this year instead of January 1, 2007. Sahak
    Abrahamyan also reported that the building works on the 38-kilometer
    part of the 40-km lot of Meghri-Kajaran are over. The estimated cost
    of the building of the 40-km lot is $35 million.

    80% of this sum are lent by the Iranian Development Bank to the
    Armenian party, while the rest will be allocated from own sources,
    reports IA Regnum.