    The Governing Council of Millenium Challenge Account-Armenia SNCO met
    at the Office of Government, presided at by GC Chairman, RA Prime
    Minister Tigran Sargsyan.


    http://www.gov.am/enversion/informatio n_centre_8/official_news_en.php?&date=12288528 00

    Wednesday, 10th of December, 2008


    The Governing Council of Millenium Challenge Account-Armenia SNCO met
    at the Office of Government, presided at by GC Chairman, RA Prime
    Minister Tigran Sargsyan.

    The Council discussed and approved a package consisting of the request
    for a tenth disbursement and attached documents, inclusive of the
    annual report, summary quarterly report, performance monitoring chart,
    disbursement pre-conditions, procurement reports, procurement and
    working plans. It was noted that under the mentioned request, the
    MCA-Armenia expects to be allocated USD 6,811,305 next quarter
    (January-March, 2009) through the general financing system. Quarterly
    expenditure will rise to USD 7,109,153.

    According to the MCA-Armenia SNCO Chief Executive Director, the
    requested funds will cover the following program activities: Rural Road
    Rehabilitation, Irrigated Agriculture, Monitoring and Evaluation,
    Program Administration and Monitoring. Ara Hovsepyan also mentioned
    that thanks to the funds available from the government, the cost of
    building activities will rise to USD 11,669,871 (without VAT) by the
    end of this quarter, with the actual and projected spending for the
    month of December totaling to USD 28,081,321.

    In particular, the following activities were carried out in the period
    under review: under the Rural Road Rehabilitation Activity, the repairs
    of a 24.5km-long road section in the western part of Armenia are
    nearing completion. Work is underway under the first-package contracts,
    including the rehabilitation of a 273km-long road section to a total
    cost of USD 60.3 million. Under the Irrigated Agriculture Activity, 4
    tertiary canals have been built in 4 rural settlements. It was noted
    that by the end of this year, there will be finalized design packages
    for 6 water-mains, 7 gravity systems and 18 pump-stations to be built
    in all marzes of the Republic next year. Over 18.000 program
    beneficiaries have so far been taught on the subject of
    intra-organizational water management and high-value output under the
    From Water-to-Market component of the Irrigated Agriculture Activity.
    Under the same program, 128 pilot farms have been created and over 130
    agricultural loans have been extended to total sum of USD 1.5 million.

    Once approved by the GC Chairman, the request package will be sent off
    to the MCC for consideration.
    The meeting similarly discussed and endorsed the draft contract on
    Rehabilitation of Six Water-Mains (Package No.1) under the
    Infrastructure component of the Irrigated Agriculture Activity.

    The council was briefed on the targets of the 2nd stage of the loan
    component of the From Water-to-Markey Activity of the Irrigated
    Agriculture Project. Then, the meeting discussed the operational
    guidelines entitled "Administrative Policy and Procedures for Lending
    Program."

    In conclusion, the council members were presented reference notes on
    the approaches and technologies used in engineering water-mains and
    tertiary canals, the audits and other checks of MCA-Armenia SNCO's
    financial and program activities etc.