    MARMARIK RESERVOIR RESTORATION LEFT INCOMPLETE DUE TO DOLLAR DEPRECIATION

    http://www.nt.am/news.php?shownews=1 15302

    YEREVAN, JULY 4, NOYAN TAPAN. On July 2, RA Prime Minister Tigran
    Sargsian visited Marmarik reservoir in the RA Kotayk region, which has
    not been used from the moment of its construction, after 1974, as its
    stronghold slided down a few days before filling the water into the
    reservoir. The stronghold top that had 350 meters length slided down to
    13.5 meters. And approximately 500 thousand cubic meters earth mass
    moved. Stronghold repairs started from 2006.

    Andranik Andreasian, the Chairman of the Water Economy State Committee
    of the RA Ministry of Territorial Administration, told the Prime
    Miniser that at present Marmarik reservoir poses certain danger for
    people living below it. According to A. Andreasian, it was one of the
    main reasons, the reservoir restoration was involved in the World Bank
    (WB) Stronghold Security Program, within the framework of which
    reservoir's stronghold was to be restored. The projecting finished in
    2005. The construction contract was signed on August 31, 2006 and
    according to the program, the construction is envisaged to be finished
    within 24 months, in 2008, but it has been left incomplete due to the
    lack of funds as a result of dollar depreciation.

    According to Andreasian, at that time the construction contract cost
    was 4bn 568m 779 thousand drams, that is, 11.521.609 dollars. The
    allocated funds have been spent, but a new calculation is needed to
    finish the rest work.