    ARMROSGASPROM TO INVEST 52BLN AMD IN ARMENIA'S GAS TRANSMISSION SYSTEM BY THE END OF NEXT YEAR

    ARKA
    Oct 20, 2008

    YEREVAN, October 20. /ARKA/. The ArmRosgasprom Company plans to invest
    a total of 52bln AMD in the expansion of Armenia's gas transmission
    system.

    "The implementation of ArmRosgasprom's system expansion program has
    necessitated the construction of a new 197.4km-long Iran-Armenia gas
    main, as well as the renovation of the currently operating 120km-long
    gas main," the company reported.

    The company has carried out necessary research and project work. The
    project will allow ArmRosgasprom to be involved in regional gas
    projects and enhance gas-supply safety sue to alternative sources.

    The second section of the gas main, Kajaran-Ararat, runs at an
    altitude of 3,000 above sea level through the Syunik Vaiots Dzor and
    Ararat regions. The construction and assembling operations are to be
    completed late this month.

    By October 1, 2008, 36,769.6mln AMD work had been carried out -
    176.7km of pipeline had been laid and 180km of pipeline trenches had
    been carried.

    The first 40km-long section, Meghri-Kajaran, was put into operation
    on March 19, 2007.