YEREVAN, DECEMBER 4, NOYAN TAPAN. The Millennium Challenge
Account-Armenia (MCA-Armenia) state nonprofit organization and Arpa
Sevan OJSC signed on December 3 a contract on construction of the
Spitak gravity-fed system. Its cost is 2,106,477 USD, the term is
16 months.
The Spitak gravity-fed system is one of the five gravity-fed systems,
whose construction has been included in "Infrastructure" activity
of MCA-Armenia's Irrigated Agriculture project. Under this activity
financed by the Millennium Challenge Corporation (MCC), also 6
main canals and 17 pumping stations will be rehabilitated, and the
irrigation network in more than 70 communities and the drainage system
of Ararat Valley will be improved.
NOYAN TAPAN
DECEMBER 4, 2009
YEREVAN
YEREVAN, DECEMBER 4, NOYAN TAPAN. The Millennium Challenge
Account-Armenia (MCA-Armenia) state nonprofit organization and Arpa
Sevan OJSC signed on December 3 a contract on construction of the
Spitak gravity-fed system. Its cost is 2,106,477 USD, the term is
16 months.
The Spitak gravity-fed system is one of the five gravity-fed systems,
whose construction has been included in "Infrastructure" activity
of MCA-Armenia's Irrigated Agriculture project. Under this activity
financed by the Millennium Challenge Corporation (MCC), also 6
main canals and 17 pumping stations will be rehabilitated, and the
irrigation network in more than 70 communities and the drainage system
of Ararat Valley will be improved.