    ARMRUSGAZPROM PLANS TO ALLOCATE 30.6 BILLION DRAMS FOR MODERNIZATION OF 5TH POWER UNIT OF HRAZDAN TPP IN 2009

    Noyan Tapan
    http://www.nt.am?shownews=1011596
    Jan 27, 2009

    ArmRusgazprom CJSC plans to make investments of 78.6 billion drams
    in 2009, including 30.6 billion drams (about 100 million USD) for
    modernization of the 5th power unit of Hrazdan Thermal Power Plant
    (TPP).

    According to the website of the company, in addition to acquiring the
    assets of 248.8 million USD of incompleted construction of Hrazdan
    TPP's 5th unit, ArmRusgazprom also assumed an obligation to complete
    the power unit's construction and modernize it under the agreement
    signed between the Armenian government and Gazprom OJSC in 2006. It
    is envisaged investing about 180 million USD for implementation of
    the project's investment stage, as a result of which a power plant
    with modern efficient gas turbines will be put into operation in
    2010. The program is being financed through an additional issue of
    shares of ArmRusgazprom CJSC - for benefit of Gazprom OJSC.