    SOFAZ HAS NOT YET ALLOCATED SUMS FOR BAKU-KARS RAILROAD CONSTRUCTION

    /PanARMENIAN.Net/
    27.05.2009 11:06 GMT+04:00

    /PanARMENIAN.Net/ This year, the State Oil Fund of Azerbaijan
    (SOFAZ) has not yet allocated considerable sums for the construction
    of Baku-Tbilisi-Kars railroad, SOFAZ Executive Director Shahmar
    Movsumov said.

    According to him, the allocated sums were envisaged for the maintenance
    of the office responsible for project implementation. "This year,
    SOFAZ plans to spend $100 million within the railroad construction
    project framework," Movsumov said.

    Azerbaijan plans to allocate $200 million from SOFAZ resources
    for the construction of the Georgian part of Baku-Tbilisi-Kars
    railroad. Additional sum of over $280 has been allocated for the
    maintenance of "Marabda-Kars Railroads" LLC. The money will be spent
    for paying salaries and covering other office expenses, Trend Capital
    reports.

    Baku-Tbilisi-Kars project also envisages the construction of a new
    branch line with a length of 105 km., with 76 km. passing across
    Turkey's territory and 29 km. passing across Georgia, Besides,
    Akhakalaki-Marabda-Tbilisi section of the railroad (183 km.) will
    be reconstructed in Georgia for increasing the throughput capacity
    to 15 million per year. It is also planned to construct a railway
    transit point in Akhaltsakhe to match the Georgian rails with European
    railroad system.