    ARARAT-YEREVAN GAS LINE RECONSTRUCTION COMPLETED

    /PanARMENIAN.Net/
    28.09.2009 18:54 GMT+04:00

    /PanARMENIAN.Net/ Ararat-Yerevan gas line reconstruction was completed,
    resulting in gas flow capacity increase, ArmRosgazprom press service
    reported. Reconstruction works were conducted using new technologies,
    without gas supply cessation.

    "Techno Fit", "Eghvardstroy" and "Snart" participated in reconstruction
    works, with ArmRosgazprom investing over AMD 1,5 billion.

    According to ArmRosgazprom CJSC Director General's Councilor,
    Iran-Armenia gas line construction manager Vladimir Margaryan,
    reconstruction aims at increasing capacity of gas flow through
    Iran-Armenia gas line to Yerevan-1, Sovetashen-2 gas-distributing
    stations, Yerevan TPP and other objects. Gas flow capacity will be
    increased to 6 million cubic meters of gas.