    ACMC SUMMARIZES THE INTERIM RESULTS OF ANTI-CRISIS IMPLEMENTATION PROGRAM

    ArmInfo
    2010-07-20 12:29:00

    ArmInfo. Agarac Copper-Molybdenum Combine summarized the interim
    results of implementation of anti-crisis investment programs under
    the Government of Armenia's stabilization loan of $ 14 million

    Let's recall that, in connection with last year's severe crises in
    the mining sphere of Armenia, which suffered from a sharp decline
    in raw material prices in the international market, the Government
    of Armenia in June 2009, in order to stimulate the development of
    the mining industry has taken the decision (according to Government
    Decision Ñ~L 719-A) for providing a budget loan to 3 largest mining
    companies "Zangezur Mining", "Armenian Molybdenum Production" and
    "Agarak Copper-Molybdenum Combine".

    ACMC was granted a loan of $ 14 million with a payment term of 4 years
    at a rate of LIBOR +8%, under a program aimed at reducing costs and
    improving competitiveness of production.

    According to the press service of GeoProMining in Armenia, which owns
    ACMC, the program involves a systematic approach, including capital
    investments to modernize production and improve the skills of middle
    management staff, as well as changes in organizational structure.

    The investment project includes modernization of the deposit and the
    reconstruction of the plant.

    Since autumn 2009 five BelAZ dump trucks of 55 ton capacity were
    brought into Armenia, which were put into operation at the open pit.

    Were obtained also wheel loader BelAZ, two wheeled tractors TK and
    one tractor with bulldozer and loosening equipments. The plant also
    acquired excavator Caterpiller 345 CL, which is in the process of
    arrival. Purchase of mining equipment is part of the anti-recessionary
    program, aimed at increasing production and promoting efficient
    operation of the mine.

    Under the program, informed the press service, in November 2009, the
    company acquired a new flotation equipment of European manufacturer
    Metso Minerals, which meets all the necessary technical requirements.

    Flotation park will be installed in the new-built complex, which will
    add additional capacity to ensure increased productivity.

    In August 2009, the Group GeoProMining commissioned the
    international company "Mekhanobr" to prepare a feasibility study
    (FS) of the reconstruction of the plant. The project itself on the
    reconstruction will be ready in December 2010. The project is an
    integrated approach to designing new and upgrading existing plant,
    including the development of efficient technologies, modern design
    solutions and use in projects of technological equipment with high
    technical and economic indicators.

    The designer offered his know-how, implementation of which will reduce
    production costs and increase the yield of the concentrate. As a
    result, increase of production: increase of the concentrate by 2-3%
    and at least 10% planned to reduce production costs.

    In turn, the Institute 'Mechanobr' signed a contract with a mining
    and metallurgical Institute of Armenia for joint cooperation in the
    project. Along with that, in June 2010 ACMC started a program for
    the exploration, which will result in grow of ore reserves at the
    deposit to 160 million tons.

    During the first half of 2010 the company fulfilled the program of
    stripping in the record volumes for the last 20 years. It is planned
    to implement the stripping work at 2.2 million cubic meters, which
    will increase the effectiveness of mine operation.

    The company began repairing and construction work as the facade and
    internal nature. For the 6 months of 2010 JSC "Agarak Copper-Molybdenum
    Combine (ACMC), compared with the volumes of production for the second
    half of 2009 increased the production of copper concentrate at 12.29%
    and molybdenum concentrate at 2.4%.

    Production volumes totaled 15 159 tons of copper and 254 tons of
    molybdenum concentrate.

    Currently, the company continues to the stages of investment program
    processes. Since December 2009 the company started to make payments
    on the loan. Total loan amount will be used in 2010. Reconstruction
    project suggests additional investment.

    Recall that a group of companies GeoProMining acquired the shares
    of Agarak Copper- molybdenum Combine" in December 2007. GeoProMining
    specializes in extraction, enrichment of polymetallic ores (copper,
    olybdenum, antimony) and precious metals (gold, silver). Deposits and
    ore-processing plants of the company are located in Armenia, Georgia,
    Russia and Vietnam.