    FEASIBILITY PLAN FOR CONSTRUCTION OF VANADZOR-FIOLETOVO RAILWAY STRETCH TO BE READY IN TEN DAYS

    /ARKA/
    AUGUST 19, 2011
    YEREVAN

    YEREVAN, August 19. / ARKA /. Armenian transport and communications
    minister Manuk Vardanian met today with representatives of Russian
    Sibgiprotrans design firm and the South Caucasus Railways, operating
    Armenia's railroads and gave them 10 days to present the feasibility
    plan for construction of a 32-km long railway stretch from Vanadzor,
    the administrative center of Lori province and Fioletovo village in
    the same province.

    Sibgiprotrans design firm and the South Caucasus Railways have been
    chosen to design the stretch.

    The press service of the ministry said the representatives of these
    companies presented a detailed draft plan, selected from five options.

    It said the work on the feasibility study will begin after the draft
    project is approved.

    The construction of the 32-km long stretch from Vanadzor to Fioletovo
    was estimated to cost $100 million. The financing will be carried out
    jointly by the Armenian and Russian sides. The Anti-Crisis Fund of the
    Eurasian Economic Community has pledged $49.9 million loan to Armenia.

    The remaining 50% of the project will be financed by Russia.

    Sibgiprotrans has 70 years of experience in the field of research
    and design and construction of transport facilities. It is one of
    the leading design company of the industry with the focus of railway
    facilities.