TendersInfo - Project Notices
December 17, 2011 Saturday
Armenia : Electricity Supply Reliability Project
The development objective of the Electricity Supply Reliability
Project is to increase the reliability and capacity of the
transmission network. There are two components to the project. The
first component of the project is strengthening of the power
transmission network. This component will finance investments in
replacement of around 230 km section of transmission line from the
Hrazdan thermal power plant to Shinuhayr substation as well as land
acquisition and possible resettlement. The investments will
rehabilitate around 45 percent of 220kV transmission lines, which need
urgent rehabilitation and upgrade. The second component of the project
is technical assistance. This component will finance: 1) training of
the staff of the High Voltage Electric Networks (HVEN) to strengthen
their capacity in technical supervision, planning, procurement,
financial management and project management; 2) computer software for
transmission network system planning and analysis; 3) project
implementation support, including supervision of field works; and 4)
incremental operating costs of the HVEN.
Approval Date : 26-MAY-2011
Closing Date : 30-JUN-2016
Total Project Cost : 52
Region Europe And Central Asia
Major Sector (Sector) (%) : Energy and mining (Power) (100%)
Themes (%) : Climate change (10%)
Other urban development (45%)
Rural services and infrastructure (45%)
country :Armenia
From: Baghdasarian
December 17, 2011 Saturday
Armenia : Electricity Supply Reliability Project
The development objective of the Electricity Supply Reliability
Project is to increase the reliability and capacity of the
transmission network. There are two components to the project. The
first component of the project is strengthening of the power
transmission network. This component will finance investments in
replacement of around 230 km section of transmission line from the
Hrazdan thermal power plant to Shinuhayr substation as well as land
acquisition and possible resettlement. The investments will
rehabilitate around 45 percent of 220kV transmission lines, which need
urgent rehabilitation and upgrade. The second component of the project
is technical assistance. This component will finance: 1) training of
the staff of the High Voltage Electric Networks (HVEN) to strengthen
their capacity in technical supervision, planning, procurement,
financial management and project management; 2) computer software for
transmission network system planning and analysis; 3) project
implementation support, including supervision of field works; and 4)
incremental operating costs of the HVEN.
Approval Date : 26-MAY-2011
Closing Date : 30-JUN-2016
Total Project Cost : 52
Region Europe And Central Asia
Major Sector (Sector) (%) : Energy and mining (Power) (100%)
Themes (%) : Climate change (10%)
Other urban development (45%)
Rural services and infrastructure (45%)
country :Armenia
From: Baghdasarian