The Electric Power Produced By " Meghri" To Be Transported To Iran

Collapse
X
 
  • Filter
  • Time
  • Show
Clear All
new posts

  • The Electric Power Produced By " Meghri" To Be Transported To Iran

    THE ELECTRIC POWER PRODUCED BY " MEGHRI" TO BE TRANSPORTED TO IRAN

    http://tehrantimes.com/economy-and-business/98498-the-electric-power-produced-by--meghri-to-be-transported-to-iran-
    On Line: 06 June 2012 15:06
    In Print: Thursday 07 June 2012

    YEREVAN, ( Armenpress): The foundation of "Meghri" HPP on the river
    Araks is scheduled in Meghri , on August 22.The construction will be
    carried out within five year time, after which the produced electric
    power is set to be transferred to Iran by 230 KV voltage electric
    wiring built by the investor.

    "In accordance with the financing scheme " Meghri" HPP construction
    will cost 323 milllion U.S. dollars" Ministry of Energy and Natural
    Resources informed Armenpress.Armen Movsisyan Armenian Minister
    of Energy and Natural Resources signed a permission contract
    with his Iranian counterpart Majid Namjoo on the basis of "
    building-ownership-operation-transfer" of "Meghri" HPP in 2010.

    This investment project was the first suchlike program implemented
    in Armenia. In accordance with the memorandum feasibility study
    of the hydro power plant was conducted by Iranian " Mahab -khods"
    consulting company, by the order of the Iran's water and energy
    development company.

    ITF's elaboration work was coordinated and monitored by
    Armenian-Iranian Joint Technical Committees.

    Two HPPs are scheduled to be built on Araks river; from Armenian side
    " Meghri" HPP, from Iranian side HPP called " Kharachilar".