    THE GROUND BREAKING OF MEGHRI HPP SCHEDULED FOR NOVEMBER 8

    YEREVAN, NOVEMBER 6, ARMENPRESS: The Republic of Armenia and the
    Islamic Republic of Iran are planning to build the most powerful hydro
    power plant in the South Caucasus namely Meghri hydro electric power
    station by the efforts made from Armenian part and "Gharachilar" HPP
    from Iranian part. Lusine Harutyunyan, Public Relations and Information
    department head, Ministry of Energy and Natural Resources stated in the
    briefing with Armenpress in accordance with the arrangement reached
    in the frame of Armenian- Iranian intergovernmental commission ,
    ground breaking of Meghri hydro electric power station is scheduled
    for November 7.

    Accordingly with the preliminary agreement , each of the stations is
    set to produce 793 million kW / h of electricity. Megri HPP capacity
    is estimated 130 MW. The construction will last for five years and
    will cost $323 million , which will be invested by Iranian investment
    company. Armenia is scheduled to return the invested money in 15
    years time by supplying electricity through Meghri HPP's 230 kV voltage