    Zerkalo: Baku-Tbilisi-Kars railway was to be commissioned in 2009;
    however it will not work in 2014 as well

    18:55 26/10/2013 » ECONOMY



    "The President of Georgia Mikheil Saakashvili completes tenure on his
    position. In his speech, he expressed great regret that he could not
    launch the project of commissioning of Baku-Tbilisi-Kars (BTK) railway
    during his presidency," Azerbaijani newspaper "Zerkalo" reads.

    The publication reminded that the construction work of Georgian
    section of BTK railway kicked off on November 21, in 2007.
    The presidents of Azerbaijan, Georgia and Turkey - Ilham Aliyev,
    Mikheil Saakashvili and Abdullah Gul - signed a symbolic document on
    launching the BTK construction. The document was placed in a capsule,
    and laid at the foundation of the railway.

    "The agreement on starting the BTC construction was signed in Tbilisi
    on February 7, in 2007, and it was expected that they will complete
    the work by the end of 2009. Unfortunately, the BTK will not be put
    into operation neither in this, nor in the upcoming year. It is
    therefore surprising when senior officials claim that the construction
    works continue in accordance with the approved schedule," wrote
    Zerkalo writes.

    As stated by the head of the transport policy of the Ministry of
    Economy and Sustainable Development of Georgia, Ketevan Salukvadze,
    while talking about the implementation of the Baku-Tbilisi-Kars
    railway project said that Georgian section of the railway will be
    completed in 2015 according to the current timetable. According to
    her, today 78% of the work on the first section (Marabda-Tetritskaro)
    is completed, as well as 54% of the work in the second section
    (Tetritskaro-Tsalka), 23% of the work in the third section
    (Tsalka-Akhalkalaki), 9% of the work on the fourth area (train
    station), 39% of the work on the railway station and 33% of the work
    on the fifth plot line (Akhalkalaki-Kartsakhi).

    Salukvadze noted that the total cost of the project in Georgia makes $
    767 million. In the framework of the "Baku-Tbilisi-Kars" a new
    105-kilometer railway branch is planned to be constructed. In
    addition, Georgia will be reconstructed Akhalkalaki-Marabda-Tbilisi
    railway section, which will increase its capacity to 15 million tons
    of cargo a year. In the future, with the completion of the Marmaray
    project (construction of a tunnel under the Bosporus) access to Europe
    will be provided by using the railway line of Baku-Tbilisi-Kars.

    In his turn, the general director of the "Marabda-Kartsakhi" company
    Oleg Bichiashvili stated that the BTK construction goes on at an
    accelerated pace, but is unlikely to be used for the withdrawal of
    NATO's military cargo from Afghanistan. The head of the company, who
    leads the project of construction of the Georgian section of the
    railway, got acquainted with the work on the future highway, on
    Thursday during the day. "In 2014 withdrawal of troops and supplies
    from Afghanistan is planned to be implemented, the opening of the
    railway is unlikely to happen before 2015," Oleg Bichiashvili told the
    reporters.

    Source: Panorama.am