    VAZASHEN-PARAVAKAR BYPASS TO BE READY AT END SEPTEMBER

    YEREVAN, August 22. /ARKA/. The construction of Vazashen-Paravakar
    bypass road in Armenia will be completed on September 30, Armenian
    deputy minister of transport and communication Artur Arakelyan said
    after the government meeting on Thursday.

    The cabinet meeting approved appropriation of an additional of 55
    million drams for construction of the road. The decision to build the
    road was made for security purposes, bearing in mind regular Azeri
    shelling on the border.

    The contractor, Ijevan road construction company, failed to cope with
    the deadlines, hence the agreement was cancelled, Arakelyan said. A
    contact will be signed with another company, but the commissioning
    deadlines will be maintained due to importance of the road section,
    he said. Blasting works have led to additional expenditures, the
    deputy minister said.

    At the meeting Armenian premier Hovik Abrahamyan suggested the ministry
    proposed to the ministry to carefully consider funding for similar
    projects so that no additional funds are required afterwards in future.

    The total length of the road is 3,188 kilometers. A 250-meter-long and
    5-meter-high protective wall is to be built as part of the construction
    to ensure security on the most dangerous section of the road. The
    cost of the project is 519.8 million drams. ($1 - 407.74 drams). -0--