Vestnik Kavkaza, Russia
July 21 2014
Yerevan power plant connected to the electric grid ahead of time
21 July 2014 - 6:51pm
One of the largest generating stations in Armenia, the Yerevan power
plant, has been reconnected to the grid after suspension for the
planned overhaul of June 3. The station was connected to the grid on
July 20 instead of the scheduled date of July 29. Planned work
included cleaning the rotor, but it turned out that the rotor does not
need to be cleaned, so the work was completed before the deadline,
said the general director of the plant, Hovakim Hovhannisyan.
The cost of the overhaul was 9.5 billion drams, and 90% of these funds
were used to purchase spare parts of the turbine. He noted that during
this repair it was possible to increase the efficiency by 1-1.5%,
which will reduce fuel consumption for electricity production.
July 21 2014
Yerevan power plant connected to the electric grid ahead of time
21 July 2014 - 6:51pm
One of the largest generating stations in Armenia, the Yerevan power
plant, has been reconnected to the grid after suspension for the
planned overhaul of June 3. The station was connected to the grid on
July 20 instead of the scheduled date of July 29. Planned work
included cleaning the rotor, but it turned out that the rotor does not
need to be cleaned, so the work was completed before the deadline,
said the general director of the plant, Hovakim Hovhannisyan.
The cost of the overhaul was 9.5 billion drams, and 90% of these funds
were used to purchase spare parts of the turbine. He noted that during
this repair it was possible to increase the efficiency by 1-1.5%,
which will reduce fuel consumption for electricity production.