Announcement

Collapse
No announcement yet.

Complete Rehabilitation Of Ashnak Substation And Yerevan Thermal Pow

Collapse
X
 
  • Filter
  • Time
  • Show
Clear All
new posts

  • Complete Rehabilitation Of Ashnak Substation And Yerevan Thermal Pow

    COMPLETE REHABILITATION OF ASHNAK SUBSTATION AND YEREVAN THERMAL POWER PLANT TO COST $69.16 MILLION

    YEREVAN, March 31. / ARKA /. The complete rehabilitation of the Ashnak
    substation and the Yerevan Thermal Power Centert through replacement
    of all key equipment will cost $69.16 million, World Bank Country
    manager for Armenia, Laura Bailey told a news conference today.

    She said it will help reduce the number and duration of equipment
    failures caused by technical reasons, and, thus, improve the
    reliability of power supply for thousands of electricity consumers.

    She said $17.6 million will be allocated by the Armenian government
    and the remaining $52 million will come as a World Bank loan.

    The US$52 million loan for the Electricity Transmission Network
    Improvement Project (ETNIP) for Armenia was approved by the World
    Bank Board of Executive Directors on March 30. The new project will
    improve the reliability of the power transmission network and system
    management, and support the Government's efforts in ensuring adequate
    electricity supply across the country.

    The World Bank will provide a US$52 million IBRD loan of variable
    spread with a 14.5-year grace period and the total repayment term of
    25 years.

    Ashnak substation was commissioned in 1983 and has undergone no major
    rehabilitation since then. This substation is essential for ensuring
    reliable power supply to consumers in Eastern and North-Eastern parts
    of Armenia, including a large dairy products company, an asphalt plant,
    and a diamond polishing and jewelry production factory, which employ
    around 3,500 people.

    Rehabilitation of the substation of the Yerevan Thermal Power Center,
    which accounts for 20 percent of total annual electricity generation
    in Armenia will help reduce the incidence of equipment failures. The
    overall cost of meeting the electricity demand in the country will
    significantly increase if it is disconnected from the grid due to
    failure of its substation. The substation was commissioned in 1965,
    and has not been rehabilitated since then.

    Ms. Bailey said under the second component - improvement of the
    power system management - establishment of a back-up dispatch
    center is envisaged which will allow improving the management of the
    power system. Specifically, it is important for ensuring continuous
    management and control of the power system in case the primary dispatch
    center (located in down-town Yerevan) fails due to technical or other
    reasons. The back-up dispatch center will allow to immediately restore
    the control and management of the power system in case of such failure.

    "Armenia's power system will need around 500 MW of new gas-fired
    generation capacity to preclude the emergence of a supply capacity
    gap by 2020," said Arthur Kochnakyan, World Bank Task Team Leader of
    the Project.

    "Preparation of a new electricity generation project is another
    critical activity that will be implemented within this project. The
    Government plans to construct a new combined cycle gas turbine,
    which will require a number of preparatory activities for which no
    financing is available,' he said.

    Since joining the World Bank in 1992 and IDA in 1993, the commitments
    to Armenia total approximately US$2,118.730 million."-0-

    http://arka.am/en/news/technology/complete_rehabilitation_of_ashnak_substation_and_y erevan_thermal_power_plant_to_cost_69_16_million/#sthash.oy8jTzGj.dpuf

Working...
X