VAZASHEN-PARAVAKAR BYPASS TO BE READY AT END SEPTEMBER
YEREVAN, August 22. /ARKA/. The construction of Vazashen-Paravakar
bypass road in Armenia will be completed on September 30, Armenian
deputy minister of transport and communication Artur Arakelyan said
after the government meeting on Thursday.
The cabinet meeting approved appropriation of an additional of 55
million drams for construction of the road. The decision to build the
road was made for security purposes, bearing in mind regular Azeri
shelling on the border.
The contractor, Ijevan road construction company, failed to cope with
the deadlines, hence the agreement was cancelled, Arakelyan said. A
contact will be signed with another company, but the commissioning
deadlines will be maintained due to importance of the road section,
he said. Blasting works have led to additional expenditures, the
deputy minister said.
At the meeting Armenian premier Hovik Abrahamyan suggested the ministry
proposed to the ministry to carefully consider funding for similar
projects so that no additional funds are required afterwards in future.
The total length of the road is 3,188 kilometers. A 250-meter-long and
5-meter-high protective wall is to be built as part of the construction
to ensure security on the most dangerous section of the road. The
cost of the project is 519.8 million drams. ($1 - 407.74 drams). -0--
http://arka.am/en/news/society/vazashen_paravakar_bypass_to_be_ready_at_end_septe mber_/#sthash.407hcPVj.dpuf
YEREVAN, August 22. /ARKA/. The construction of Vazashen-Paravakar
bypass road in Armenia will be completed on September 30, Armenian
deputy minister of transport and communication Artur Arakelyan said
after the government meeting on Thursday.
The cabinet meeting approved appropriation of an additional of 55
million drams for construction of the road. The decision to build the
road was made for security purposes, bearing in mind regular Azeri
shelling on the border.
The contractor, Ijevan road construction company, failed to cope with
the deadlines, hence the agreement was cancelled, Arakelyan said. A
contact will be signed with another company, but the commissioning
deadlines will be maintained due to importance of the road section,
he said. Blasting works have led to additional expenditures, the
deputy minister said.
At the meeting Armenian premier Hovik Abrahamyan suggested the ministry
proposed to the ministry to carefully consider funding for similar
projects so that no additional funds are required afterwards in future.
The total length of the road is 3,188 kilometers. A 250-meter-long and
5-meter-high protective wall is to be built as part of the construction
to ensure security on the most dangerous section of the road. The
cost of the project is 519.8 million drams. ($1 - 407.74 drams). -0--